What Does It Cost to Build a Single 10x10 Room in India?
Whether you are adding a room to an existing house, building a shop, a store room, or a small rental unit — the 10x10 ft room is the most basic construction unit people ask about.
Here is the quick answer: a 10x10 ft room costs ₹80,000–₹2,50,000 in India in 2026, depending on whether you want bare structure or full finishing.
This guide gives you the exact material list, quantities, labour charges, and total cost — both with and without finishing.
Room Specifications (Assumptions)
Before calculating cost, let us define what we are building:
- Room size: 10 ft x 10 ft (floor area = 100 sq ft)
- Height: 10 ft (standard residential)
- Wall thickness: 9 inches (external/load-bearing) or 4.5 inches (partition)
- Roof: RCC slab, 5 inches (125mm) thick
- Foundation: Simple strip foundation, 3 ft depth
- One door: 3 ft x 7 ft
- One window: 3 ft x 4 ft
Cost Breakdown: Structure Only (Without Finishing)
This covers foundation, walls, and roof slab — the bare minimum to enclose a room.
Foundation
| Item | Quantity | Rate | Cost |
|---|---|---|---|
| Excavation (3 ft deep, 1.5 ft wide) | 2.5 m³ | ₹300/m³ | ₹750 |
| PCC in foundation (1:4:8) | 0.5 m³ | ₹5,000/m³ | ₹2,500 |
| Rubble/brick masonry in foundation | 2.0 m³ | ₹4,000/m³ | ₹8,000 |
| DPC | Lump sum | — | ₹1,500 |
| Foundation subtotal | ₹12,750 |
Walls (9-inch brick walls)
| Item | Quantity | Rate | Cost |
|---|---|---|---|
| Bricks (1st class) | 1,500 nos | ₹8/brick | ₹12,000 |
| Cement for mortar (1:6) | 38 bags | ₹390/bag | ₹14,820 |
| Sand for mortar | 2.2 m³ | ₹4,000/m³ | ₹8,800 |
| Mason labour | 8.5 m³ | ₹1,000/m³ | ₹8,500 |
| Helper labour | — | Lump sum | ₹3,500 |
| Wall subtotal | ₹47,620 |
RCC Roof Slab (125mm thick, M20 grade)
| Item | Quantity | Rate | Cost |
|---|---|---|---|
| Concrete (M20 ready-mix or site-mix) | 1.5 m³ | ₹6,500/m³ | ₹9,750 |
| Steel (TMT Fe500D) | 120–150 kg | ₹60/kg | ₹7,200–₹9,000 |
| Shuttering (plywood + props) | 100 sq ft | ₹55/sq ft | ₹5,500 |
| Shuttering labour | — | Lump sum | ₹3,000 |
| Slab casting labour | — | Lump sum | ₹3,500 |
| Slab subtotal | ₹28,950–₹30,750 |
Structure-Only Total
| Component | Cost |
|---|---|
| Foundation | ₹12,750 |
| Walls | ₹47,620 |
| RCC slab | ₹28,950–₹30,750 |
| Total (structure only) | ₹89,320–₹91,120 |
Round figure: ₹90,000–₹1,00,000 for basic structure in a tier-2 city.
Cost Breakdown: With Complete Finishing
Now add plastering, flooring, door, window, electrical, and painting.
Plastering
| Item | Area | Rate | Cost |
|---|---|---|---|
| Internal plastering (12mm, 1:6) | 380 sq ft | ₹25/sq ft | ₹9,500 |
| External plastering (20mm, 1:4) | 180 sq ft | ₹32/sq ft | ₹5,760 |
| Plastering subtotal | ₹15,260 |
Flooring
| Type | Area | Rate | Cost |
|---|---|---|---|
| Cement flooring | 100 sq ft | ₹30/sq ft | ₹3,000 |
| OR Vitrified tiles | 100 sq ft | ₹75/sq ft (with laying) | ₹7,500 |
Door and Window
| Item | Qty | Rate | Cost |
|---|---|---|---|
| Flush door with frame | 1 | ₹5,500 | ₹5,500 |
| Window (aluminium, 3x4 ft) | 1 | ₹4,000 | ₹4,000 |
| Subtotal | ₹9,500 |
Electrical
| Item | Cost |
|---|---|
| Wiring (2 light points, 2 plug points, 1 fan point) | ₹4,000–₹6,000 |
| MCB box + switch board | ₹1,500–₹2,500 |
| Electrical subtotal | ₹5,500–₹8,500 |
Painting
| Type | Area | Rate | Cost |
|---|---|---|---|
| Emulsion paint (2 coats) | 380 sq ft interior | ₹18/sq ft | ₹6,840 |
| External weather coat | 180 sq ft | ₹22/sq ft | ₹3,960 |
| Painting subtotal | ₹10,800 |
Complete Room Total (With Finishing)
| Component | Cost |
|---|---|
| Structure (foundation + walls + slab) | ₹90,000–₹1,00,000 |
| Plastering | ₹15,260 |
| Flooring (vitrified tiles) | ₹7,500 |
| Door + window | ₹9,500 |
| Electrical | ₹5,500–₹8,500 |
| Painting | ₹10,800 |
| Total (with finishing) | ₹1,38,560–₹1,51,560 |
Round figure: ₹1,40,000–₹1,60,000 for a fully finished 10x10 room in a tier-2 city.
In metros like Mumbai or Bangalore, add 30–50% to these numbers. In rural areas, subtract 20–30%.
Complete Material List for 10x10 Room
Here is everything you need to order:
| Material | Quantity | Approx Cost |
|---|---|---|
| Bricks (1st class) | 1,500 nos | ₹12,000 |
| Cement (OPC 53, 50 kg) | 55–70 bags | ₹21,450–₹27,300 |
| Sand (river/M-sand) | 4–5 m³ | ₹16,000–₹25,000 |
| Aggregate (20mm) | 1.5–2 m³ | ₹3,000–₹4,000 |
| Steel TMT bars | 120–150 kg | ₹7,200–₹9,000 |
| Vitrified tiles | 110 sq ft (10% extra) | ₹3,500–₹5,500 |
| Flush door + frame | 1 | ₹5,500 |
| Aluminium window | 1 | ₹4,000 |
| Electrical (wiring, switches) | Lump sum | ₹5,500–₹8,500 |
| Paint (interior + exterior) | As required | ₹4,000–₹6,000 |
The total cement count (55–70 bags) covers brickwork mortar, slab concrete, plastering, and flooring. Use our brick calculator to get exact brick and mortar quantities for your wall dimensions.
City-Wise Cost for 10x10 Room (With Finishing)
| City | Estimated Cost |
|---|---|
| Mumbai | ₹2,00,000–₹2,80,000 |
| Delhi NCR | ₹1,80,000–₹2,50,000 |
| Bangalore | ₹1,70,000–₹2,40,000 |
| Pune | ₹1,60,000–₹2,20,000 |
| Jaipur | ₹1,20,000–₹1,60,000 |
| Lucknow | ₹1,10,000–₹1,50,000 |
| Patna | ₹1,00,000–₹1,40,000 |
| Rural/village | ₹80,000–₹1,20,000 |
4.5-Inch Wall vs 9-Inch Wall: What Changes?
If you are building a partition wall or non-load-bearing room, you can use 4.5-inch walls instead of 9-inch. Here is how the cost changes:
| Parameter | 9-inch Wall | 4.5-inch Wall |
|---|---|---|
| Bricks needed | 1,500 | 780 |
| Cement for mortar | 38 bags | 20 bags |
| Sand | 2.2 m³ | 1.2 m³ |
| Wall cost | ₹47,620 | ₹26,000 |
| Savings | — | ₹21,620 (45%) |
However, 4.5-inch walls cannot support a roof slab directly. You will need an RCC beam ring (lintel band) to distribute the slab load. This adds ₹8,000–₹12,000 but is still cheaper overall.
How to Save Money on Single Room Construction
-
Use load-bearing walls. For a single room, you do not need RCC columns. 9-inch brick walls can support the roof slab directly — saving you the cost of columns and beams.
-
Skip external plastering if budget is tight. You can do a neat pointing finish on external brickwork. It looks decent and saves ₹5,000–₹6,000.
-
Use cement flooring instead of tiles. Saves ₹4,000–₹5,000 on a 100 sq ft room. You can always add tiles later.
-
Buy bricks and sand locally. Transport cost is often 30–40% of material cost for these heavy items. Source from the nearest supplier.
-
Track all expenses in the Yojo app. Even for a single room, material pilferage and over-ordering happen. Log every purchase and delivery to keep your budget honest.
Use the Free Calculator
Do not want to calculate all this by hand? Use our house construction cost calculator to get an instant estimate. For brick and mortar quantities specifically, the brick calculator gives you exact numbers for any room size and wall thickness.
Conclusion
A single 10x10 ft room in India costs about ₹90,000–₹1,00,000 for bare structure and ₹1,40,000–₹1,60,000 with full finishing in a tier-2 city. In metros, expect 30–50% higher. The key cost drivers are brickwork and the RCC slab. Plan your material quantities accurately, avoid wastage, and you can build a solid room without overspending.
Construction Management Expert
Senior Construction Consultant at Yojo
10+ years of experience
Reviewed on 10 April 2026
About Yojo Team
Construction management expert with 10+ years of experience helping Indian contractors build better businesses. Specialized in digital transformation for construction sites.
Related Pages
Explore by City
Mumbai Material Rates Today
Current market rates for construction materials in Mumbai, Maharashtra
Rates are indicative and may vary by supplier and location
View Mumbai page →


