Introduction

Plastering is a finishing operation applied to brick, stone, or concrete surfaces to provide a smooth, durable surface suitable for painting or decorative finishes. It accounts for a significant portion of the finishing cost in any building project.

This guide provides a complete rate analysis for both internal plastering (12mm thick, 1:6 ratio) and external plastering (20mm thick, 1:4 ratio) per square metre, along with cost comparisons for POP (Plaster of Paris) and gypsum plaster alternatives.

Types of Plaster Finishes

TypeThicknessMix ratioApplication
Internal cement plaster12mm (single coat)1:6 (CM)Interior walls and ceilings
Internal cement plaster15mm (two coats)1:4 + 1:6Where smoother finish is needed
External cement plaster20mm (two coats)1:4 (CM)External walls exposed to weather
Neeru (lime) finish2-3mmLime puttySmooth finish coat over base plaster
POP finish2-3mmPlaster of ParisSmooth finish for painting
Gypsum plaster11-15mmReady-mix gypsumInternal walls — single coat replacement

Rate Analysis: Internal Plastering (12mm, 1:6 CM)

Material Quantities per Square Metre

Wet volume of plaster per sq m:

  • Area = 1 sq m, Thickness = 12mm = 0.012 m
  • Wet volume = 1 x 0.012 = 0.012 cum

Dry volume (with 30% bulking factor):

  • Dry volume = 0.012 x 1.30 = 0.0156 cum

Cement quantity (1:6 ratio):

  • Total parts = 1 + 6 = 7
  • Cement volume = (1/7) x 0.0156 = 0.00223 cum
  • Cement weight = 0.00223 x 1,440 = 3.21 kg
  • Cement bags = 3.21 / 50 = 0.064 bags per sq m

With 5% wastage: 0.067 bags (approximately 0.22 bags per 3.3 sq m, or roughly 1 bag covers 15 sq m).

Sand quantity:

  • Sand volume = (6/7) x 0.0156 = 0.0134 cum
  • With 10% wastage/bulking: 0.015 cum per sq m

Or roughly 1 cum of sand covers 67 sq m of 12mm plaster.

Material Cost per Square Metre — 12mm Internal Plaster (1:6)

ItemQuantity per sq mRate (Rs)Amount (Rs)
OPC 43-grade cement0.064 bagsRs 380/bag24.32
Sand0.0134 cumRs 3,500/cum46.90
Water~3 litres0.50
Materials total71.72

Labour Cost

ComponentRate per sq m (Rs)
Plastering (mason + helper)25-35
Scaffolding (if above 3m)3-5
Curing (7 days)2-3
Total labour30-43

Total Rate — Internal Plaster (12mm, 1:6)

ComponentAmount per sq m (Rs)
Materials71.72
Labour (average)35.00
Sundries (2%)2.13
Sub-total108.85
Overhead + profit (15%)16.33
Total~125 per sq m

Practical market rate: Rs 28-45 per sq m (labour only) or Rs 100-130 per sq m (material + labour inclusive).

Rate Analysis: External Plastering (20mm, 1:4 CM)

Material Quantities per Square Metre

External plaster uses a richer mix (1:4) and is 20mm thick for weather resistance.

Wet volume per sq m:

  • 1 x 0.020 = 0.020 cum

Dry volume:

  • 0.020 x 1.30 = 0.026 cum

Cement (1:4 ratio):

  • Total parts = 1 + 4 = 5
  • Cement volume = (1/5) x 0.026 = 0.0052 cum
  • Weight = 0.0052 x 1,440 = 7.49 kg
  • Bags = 7.49 / 50 = 0.15 bags per sq m
  • With wastage: 0.16 bags per sq m

Sand:

  • Sand = (4/5) x 0.026 = 0.0208 cum
  • With wastage: 0.023 cum per sq m

Cost Breakdown per Square Metre — 20mm External Plaster (1:4)

ItemQuantity per sq mRate (Rs)Amount (Rs)
OPC 43-grade cement0.16 bagsRs 380/bag60.80
Sand0.023 cumRs 3,500/cum80.50
Water~5 litres0.80
Materials total142.10

Labour Cost

ComponentRate per sq m (Rs)
Plastering (mason + helper)35-50
Scaffolding erection and removal8-15
Curing (7 days)3-5
Roughcast/dash finish (if required)5-10
Total labour51-80

Total Rate — External Plaster (20mm, 1:4)

ComponentAmount per sq m (Rs)
Materials142.10
Labour (average)65.00
Sundries (3%)6.21
Sub-total213.31
Overhead + profit (15%)32.00
Total~245 per sq m

Practical market rate: Rs 40-65 per sq m (labour only) or Rs 200-260 per sq m (material + labour inclusive).

Comparison Table — Internal vs External Plaster

ParameterInternal (12mm, 1:6)External (20mm, 1:4)
Thickness12mm20mm
Mix ratio1:61:4
Cement per sq m0.064 bags (3.2 kg)0.16 bags (7.5 kg)
Sand per sq m0.0134 cum0.023 cum
Material cost per sq mRs 72Rs 142
Labour cost per sq mRs 30-43Rs 51-80
Total rate per sq mRs 100-130Rs 200-260
Cement per 100 sq m6.4 bags16 bags
Sand per 100 sq m1.34 cum2.3 cum

External plaster costs approximately 1.8 to 2 times more than internal plaster due to thicker application, richer cement mix, and scaffolding requirements.

POP and Gypsum Plaster Alternatives

POP (Plaster of Paris) Finish

POP is applied as a 2-3mm finishing coat over the base cement plaster (not a replacement).

ItemQuantity per sq mRate (Rs)Amount (Rs)
POP powder1.5-2.0 kgRs 12-15/kg18-30
Labour (application)15-25
Sanding and finishing5-8
Total POP finish38-63 per sq m

POP gives a very smooth, paint-ready finish but:

  • Adds cost on top of base cement plaster
  • Cannot be used in wet areas (bathrooms)
  • Develops cracks if base plaster has not cured properly

Gypsum Plaster (Single Coat)

Gypsum plaster is a complete replacement for internal cement plaster — applied directly on brick/block surfaces in a single coat of 11-13mm.

ItemQuantity per sq mRate (Rs)Amount (Rs)
Ready-mix gypsum plaster10-12 kgRs 8-10/kg80-120
Labour (application)20-30
Total gypsum plaster100-150 per sq m

Advantages of gypsum plaster:

  • No curing water required (saves 7-14 days of curing labour and water)
  • Smoother finish — eliminates POP layer
  • No shrinkage cracks
  • Sets in 24-48 hours (faster project completion)
  • Better fire resistance

Limitations:

  • Not suitable for external walls or wet areas
  • Higher material cost than cement plaster
  • Requires trained applicators

Cost Comparison Summary

Plaster systemCost per sq m (Rs)CuringFinish quality
Cement plaster 12mm (1:6)100-1307 daysNeeds POP/putty for painting
Cement plaster + POP finish138-1937 days + 1 daySmooth, paint-ready
Gypsum plaster 12mm100-150No curingSmooth, paint-ready
Cement plaster + wall putty125-1707 days + 1 daySmooth, paint-ready

IS Code References

  • IS 1661:1972 — Code of practice for application of cement and cement-lime plaster finishes. Specifies surface preparation, thickness, mix ratios, and curing requirements.
  • IS 1270:2007 — Specification for gypsum plaster. Covers setting time, fineness, and compressive strength requirements.
  • IS 2250:1981 — Code of practice for preparation and use of masonry mortars. Applicable to plastering mortars as well.
  • IS 1200 Part 12 — Measurement of plastering work in square metres, categorised by thickness and mix ratio.

Wastage Factors

MaterialNormal wastageWastage on uneven surfaces
Cement3-5%8-10%
Sand8-10%12-15%
POP5-8%10-12%
Gypsum plaster5-8%10-15%
Water10%15%

Uneven brick or block surfaces (out-of-plumb walls, honeycombed concrete) can increase plaster thickness by 5-10mm in patches, raising material consumption by 15-20%.

Practical Tips

  1. Wet the surface before applying cement plaster — dry bricks absorb moisture from mortar, causing poor bonding and cracks.
  2. Chicken mesh on concrete-brick junctions — Apply galvanised chicken mesh (Rs 8-12/sq ft) at junctions of RCC and brickwork to prevent crack propagation.
  3. External plaster in two coats — Apply 15mm base coat first, scratch the surface, wait 24 hours, then apply 5mm finish coat. Single-coat thick application leads to sagging and cracking.
  4. Avoid plastering in extreme heat — Summer temperatures above 40 degrees C cause rapid moisture loss. Plaster early morning or late evening, and cure immediately.
  5. Use waterproof plaster externally — Add waterproofing compound (Sika, Dr. Fixit) at Rs 3-5/sq m extra for external walls exposed to rain.

Next Steps

सामग्री लागत की गणना करें

अपनी परियोजना लागत का अनुमान लगाने के लिए हमारे कैलकुलेटर का उपयोग करें।

कैलकुलेटर खोलें
इस लेख को साझा करें:
समीक्षा की गई

निर्माण प्रबंधन विशेषज्ञ

वरिष्ठ निर्माण सलाहकार at Yojo

10+ वर्षों का अनुभवप्रमाणित निर्माण प्रबंधक

10+ वर्ष अनुभव

समीक्षा की तारीख 6 अप्रैल 2026

Y

Yojo Team के बारे में

10+ वर्षों के अनुभव वाले निर्माण प्रबंधन विशेषज्ञ, भारतीय ठेकेदारों को बेहतर व्यवसाय बनाने में मदद करते हैं। निर्माण साइटों के लिए डिजिटल परिवर्तन में विशेषज्ञ।

निर्माण प्रबंधन विशेषज्ञ10+ वर्षों का अनुभव
विशेषज्ञता:
निर्माण प्रबंधनश्रम प्रबंधनसाइट संचालन

अक्सर पूछे जाने वाले प्रश्न

Yojo ऐप डाउनलोड करें

WhatsApp पर Play Store लिंक पाएं।

मुफ्त डाउनलोड

आप भी पसंद कर सकते हैं

Introduction to Estimating and Costing in Construction
Cost & Estimation

Introduction to Estimating and Costing in Construction

Learn what estimating and costing means in construction, why it matters for contractors, the types of estimates, and what data you need before starting.

और पढ़ें
Rate Analysis for Construction in India
Cost & Estimation

Rate Analysis for Construction in India

Learn how to analyse and fix rates for construction items—lead statements, material cost, labour cost, and worked examples for plastering and masonry.

और पढ़ें
1000 Sq Ft Ghar Banana Ka Kharcha 2026 — Pura Hisab
Cost & Estimation

1000 Sq Ft Ghar Banana Ka Kharcha 2026 — Pura Hisab

2026 mein 1000 sq ft ghar banana ka kharcha ₹12–₹22 lakh aata hai. Material, labour, foundation se finishing tak — pura cost breakdown yahan dekhein।

और पढ़ें
Cement Kitna Lagega? — Free Calculation Guide
Cost & Estimation

Cement Kitna Lagega? — Free Calculation Guide

Cement kitna lagega — har kaam ke liye cement calculate karna seekhein. Brickwork, plastering, RCC slab, flooring ka complete formula aur table।

और पढ़ें
Ek Kamre Mein Kitni Eent Lagti Hai? — Complete Guide
Cost & Estimation

Ek Kamre Mein Kitni Eent Lagti Hai? — Complete Guide

10x10 ft kamre mein 1,200–1,600 eentein lagti hain (9 inch wall). Eent calculation ka formula, table, aur room size ke hisab se complete guide।

और पढ़ें
ईंट चिनाई के लिए सीमेंट मोर्टार गणना — 1:4 और 1:6 रेशियो
Cost & Estimation

ईंट चिनाई के लिए सीमेंट मोर्टार गणना — 1:4 और 1:6 रेशियो

ईंट मोर्टार के लिए सीमेंट और रेत की step-by-step गणना — 1:4 और 1:6 रेशियो। Dry volume factor 1.33 की पूरी समझ, 1 cubic metre और 100 sq ft दीवार के worked examples के साथ।

और पढ़ें

साइट से सैलरी तक, सब ट्रैक करें

Yojo डाउनलोड करें

एंड्रॉइड पर मुफ्त

Get it on Google Play
Yojo app language selection — Hindi, Marathi, Tamil and more
Yojo construction app dashboard