Rate Analysis for Construction in India: Plastering, Masonry & Concrete Rates

Analyse and fix construction rates with worked examples: lead statements, material cost, labour cost. Detailed examples for plastering, masonry & concrete.

5 min read
By Yojo Team
अंतिम अपडेट: 18 मई 2026FRESH

मूल रूप से प्रकाशित: 10 मार्च 2026

Rate Analysis for Construction in India: Plastering, Masonry & Concrete Rates - योजो निर्माण प्रबंधन ब्लॉग

Introduction

Rate analysis (or data) is the process of working out the cost per unit of each item—e.g., ₹/cum for brickwork, ₹/sq m for plastering.

The rate depends on:

  • Specifications (quality, proportion, method)
  • Material quantities and costs
  • Labour types and wages
  • Site location and conveyance
  • Overheads and profit

This guide explains the process with lead statements and worked examples.

Purpose of Rate Analysis

  1. Unit cost – Actual cost per unit of work
  2. Economy – Identify economical materials and methods
  3. Extra items – Price items not in the contract
  4. Schedule revision – Update rates when material or labour costs change

Lead Statement

Lead = Distance from source of material to construction site (in km).

Conveyance cost depends on lead and road type:

Road typeFactor
Metalled road (MT)1.0
Cart track (CT)1.1
Sandy track (ST)1.4

Equivalent lead = (Lead in MT × 1.0) + (Lead in CT × 1.1) + (Lead in ST × 1.4)

Conveyance charge = Equivalent lead × Rate per km

Example Lead Statement

MaterialRate at sourceLead (km)ConveyanceTotal at site
MTCTST
40 mm HBG metal₹120/cum57
River sand₹15/cum326
Cement₹135/bag24

Material Cost Formulae

Cement (density 1440 kg/cum)

  • 1 bag = 50 kg
  • Cost per cum cement = (Cost per bag / 50) × 1440

Wet vs Dry Concrete

  • 1 cum wet concrete ≈ 1.52 cum dry materials (bulking)
  • Weight of concrete ≈ 1440 kg/cum

Cement in Concrete (e.g., 1:2:4)

Cement (bags) = [1 / (1+2+4)] × 1.52 × Volume × (1440/50)

For 20 cum RCC (1:2:4):

  • Cement = (1/7) × 1.52 × 20 × 28.8 ≈ 125 bags
  • Sand = (2/7) × 1.52 × 20 = 8.69 cum
  • Coarse aggregate = (4/7) × 1.52 × 20 = 17.37 cum

Cement in Mortar (e.g., 1:4)

Cement fills voids in sand. For 1 cum CM (1:4):

  • Cement = (1/4) × 1 = 0.25 cum = 7.2 bags
  • Sand = (4/4) × 1 = 1 cum

Labour Classification

TypeTypical shareUse
Skilled I class30%Mason I, Brick layer I
Skilled II class70%Mason II, Brick layer II
UnskilledMazdoor (men/women)

Rates are taken from standard schedule of rates. For current Indian rates, see our labour rates guide.

Worked Example 1: Plastering CM (1:4), 20 mm Thick, 10 sq m

Data (per 10 sq m):

  • 0.21 cum CM (1:4)
  • 0.66 no. Brick layer I class
  • 1.54 no. Brick layer II class
  • 0.5 no. Men mazdoor
  • 3.2 no. Women mazdoor
  • L.S. sundries

Lead statement: Sand ₹112/cum at site, Cement ₹2,100/tonne at site.

Cost of CM (1:4) for 0.21 cum:

  • Cement = (1/4) × 0.21 × 1.44 × 2100 = ₹158.76
  • Sand = (4/4) × 0.21 × 112 = ₹23.52
  • Total = ₹182.28

Labour (illustrative rates): Mason I ₹100/day, Mason II ₹80/day, Mazdoor ₹60/day, Mixing ₹16/cum.

ItemQtyRateAmount (₹)
CM (1:4)0.21 cum182.28/0.21182.28
Brick layer I0.6610066.00
Brick layer II1.5480123.20
Men mazdoor0.56030.00
Women mazdoor3.260192.00
Mixing0.21 cum163.36
SundriesL.S.3.36
Total₹625 per 10 sq m

Rate = ₹62.50 per sq m.

Worked Example 2: RR Masonry in CM (1:6), 1 cum

Data (per 1 cum):

  • 1.1 cum rough stone
  • 0.34 cum CM (1:6)
  • 0.54 no. Mason I
  • 1.26 no. Mason II
  • 1.4 no. Men mazdoor
  • 1.4 no. Women mazdoor
  • L.S. sundries

Lead statement: Stone ₹350/cum, Sand ₹112/cum, Cement ₹2,100/tonne at site.

Cost of CM (1:6) for 0.34 cum:

  • Cement = (1/6) × 0.34 × 1.44 × 2100 = ₹171.36
  • Sand = (6/6) × 0.34 × 112 = ₹38.08
  • Total = ₹209.44
ItemQtyRateAmount (₹)
Rough stone1.1 cum350385.00
CM (1:6)0.34 cum209.44209.44
Mason I0.5410054.00
Mason II1.2680100.80
Men mazdoor1.46084.00
Women mazdoor1.46084.00
Mixing0.34 cum165.44
SundriesL.S.18.04
Total₹941 per cum

Overheads and Profit

Typical additions:

  • Tools & plant – 1–2% of estimate
  • Overheads – 4% (office, depreciation, staff, etc.)
  • Contractor profit – 8–10% (if not already in rate)

These may be built into the unit rate or added at the end of the abstract.

Next Steps

सामग्री लागत की गणना करें

अपनी परियोजना लागत का अनुमान लगाने के लिए हमारे कैलकुलेटर का उपयोग करें।

कैलकुलेटर खोलें
इस लेख को साझा करें:
समीक्षा की गई

निर्माण प्रबंधन विशेषज्ञ

वरिष्ठ निर्माण सलाहकार at Yojo

10+ वर्षों का अनुभवप्रमाणित निर्माण प्रबंधक

10+ वर्ष अनुभव

समीक्षा की तारीख 18 मई 2026

Y

Yojo Team के बारे में

10+ वर्षों के अनुभव वाले निर्माण प्रबंधन विशेषज्ञ, भारतीय ठेकेदारों को बेहतर व्यवसाय बनाने में मदद करते हैं। निर्माण साइटों के लिए डिजिटल परिवर्तन में विशेषज्ञ।

निर्माण प्रबंधन विशेषज्ञ10+ वर्षों का अनुभव
विशेषज्ञता:
निर्माण प्रबंधनश्रम प्रबंधनसाइट संचालन

अक्सर पूछे जाने वाले प्रश्न

Yojo ऐप डाउनलोड करें

WhatsApp पर Play Store लिंक पाएं।

मुफ्त डाउनलोड

आप भी पसंद कर सकते हैं

Detailed Estimate of Buildings: Step-by-Step Guide (Free Format Inside)
Cost & Estimation

Detailed Estimate of Buildings: Step-by-Step Guide (Free Format Inside)

Prepare detailed building estimates in 7 steps — measurement forms, abstract of cost, item-wise rates. Single-room + two-room examples with free format inside.

और पढ़ें
निर्माण मजदूरी दरें 2026: राजमिस्त्री ₹600–₹900/दिन | राज्यवार
Cost & Estimation

निर्माण मजदूरी दरें 2026: राजमिस्त्री ₹600–₹900/दिन | राज्यवार

राजमिस्त्री ₹600–900, बढ़ई ₹650–1,000, हेल्पर ₹450–650/दिन। 28 राज्यों की दरें तुलना करें। मुफ्त लेबर कॉस्ट कैलकुलेटर—अभी आज़माएं।

और पढ़ें
10×10 कमरा: कितनी ईंट, सीमेंट, रेत चाहिए? | मुफ्त कैलकुलेटर
Cost & Estimation

10×10 कमरा: कितनी ईंट, सीमेंट, रेत चाहिए? | मुफ्त कैलकुलेटर

10×10 फुट कमरे में ~1,450 ईंटें (₹7,250), 35 सीमेंट बैग (₹12,250), 2.5 m³ रेत। अपने कमरे का साइज़ डालें, तुरंत अनुमान पाएं।

और पढ़ें
1000 Sq Ft Ghar Banana Ka Kharcha 2026 — Pura Hisab
Cost & Estimation

1000 Sq Ft Ghar Banana Ka Kharcha 2026 — Pura Hisab

2026 mein 1000 sq ft ghar banana ka kharcha ₹12–₹22 lakh aata hai. Material, labour, foundation se finishing tak — pura cost breakdown yahan dekhein।

और पढ़ें
Cement Kitna Lagega? — Free Calculation Guide
Cost & Estimation

Cement Kitna Lagega? — Free Calculation Guide

Cement kitna lagega — har kaam ke liye cement calculate karna seekhein. Brickwork, plastering, RCC slab, flooring ka complete formula aur table।

और पढ़ें
Ek Kamre Mein Kitni Eent Lagti Hai? — Complete Guide
Cost & Estimation

Ek Kamre Mein Kitni Eent Lagti Hai? — Complete Guide

10x10 ft kamre mein 1,200–1,600 eentein lagti hain (9 inch wall). Eent calculation ka formula, table, aur room size ke hisab se complete guide।

और पढ़ें

साइट से सैलरी तक, सब ट्रैक करें

Yojo डाउनलोड करें

एंड्रॉइड पर मुफ्त

Get it on Google Play
Yojo app language selection — Hindi, Marathi, Tamil and more
Yojo construction app dashboard