Introduction
Earthwork includes excavation (cutting) and filling (embankment). It is measured in cubic metres as per IS 1200 and forms a major part of foundation and road estimates.
This guide covers:
- Simple excavation (foundations, trenches)
- Trapezoidal and prismoidal formulae for linear earthwork
- Bulking and compaction factors
Units (IS 1200)
| Item | Unit | Payment |
|---|---|---|
| Earthwork in excavation | cum | per cum |
| Earthwork in filling (foundation trenches) | cum | per cum |
| Earthwork in filling (plinth) | cum | per cum |
Simple Excavation (Buildings)
For foundation trenches, use:
Volume = Length × Breadth × Depth
- Length, breadth – At bottom of excavation (or average of top and bottom)
- Depth – From ground level to bottom of excavation
For stepped excavation, find volume of each step and add.
Example: Foundation Trench
Single room, centre line 19.2 m, trench width 0.9 m, depth 1.4 m.
Volume = 19.2 × 0.9 × 1.4 = 24.192 cum
See quantity takeoff methods for long wall–short wall and centre line approaches.
Trapezoidal Formula (Mean Area Method)
For roads, canals, or any linear work with cross-sections at regular intervals:
V = (D/2) × (A₁ + 2A₂ + 2A₃ + ... + 2Aₙ₋₁ + Aₙ)
Where:
- A₁, A₂, ... Aₙ = areas of consecutive cross-sections (sq m)
- D = distance between sections (m)
- n = number of sections
Simplified (Two Sections)
V = (D/2) × (A₁ + A₂)
Example
| Chainage | Area (sq m) |
|---|---|
| 0 | 20 |
| 10 m | 25 |
| 20 m | 18 |
| 30 m | 22 |
D = 10 m
V = (10/2) × (20 + 2×25 + 2×18 + 22) = 5 × 128 = 640 cum
Prismoidal Formula
More accurate when cross-sections change. Use when number of sections is odd (3, 5, 7...):
V = (D/6) × (A₁ + Aₙ + 4×(A₂ + A₄ + A₆ + ...) + 2×(A₃ + A₅ + A₇ + ...))
Odd subscript: multiply by 4
Even (middle): multiply by 2
Example (5 sections)
A₁=20, A₂=25, A₃=18, A₄=22, A₅=19, D=10 m
V = (10/6) × (20 + 19 + 4×(25+22) + 2×18)
= (10/6) × (39 + 188 + 36) = (10/6) × 263 ≈ 438 cum
Bulking and Compaction
Bulking
Excavated soil occupies more volume than in-situ:
- Sand: ~10–15%
- Ordinary soil: ~15–25%
- Clay: ~20–30%
Bulking factor = Volume after excavation / Volume in-situ
e.g., 1.2 means 20% bulking.
Compaction
Fill is compacted to required density. Compaction factor = In-situ volume / Compacted volume
Often 0.9–0.95 (i.e., 1 cum fill needs 1.05–1.1 cum loose soil).
Application
- Excavation to fill:
Fill volume (compacted) × (1 + bulking) ≈ Excavation required - Borrow pit:
Order more excavated material than fill volume if transporting from elsewhere.
Volume from Spot Levels
For irregular terrain (e.g., building site):
- Take grid of spot levels.
- Find cut/fill at each grid point (depth below/above formation).
- Use formula:
V = (A/4) × (Σ h at corners)
Where A = area of one grid cell, h = cut/fill depth.
For prismoid over each cell: V = (A/4) × (h₁ + h₂ + h₃ + h₄).
Side Slopes
For trapezoidal cross-section (road in cutting/filling):
Area = (B + s×h) × h
(approximate for uniform slope)
Where:
- B = bottom width
- h = depth of cut or fill
- s = horizontal distance per 1 m vertical (e.g., 1.5:1 → s = 1.5)
Measurement Rules
-
Linear – to nearest 0.01 m
-
Area – to nearest 0.01 sq m
-
Volume – to nearest 0.01 cum
-
Same work, different conditions – measure separately (e.g., soft soil vs hard rock excavation).
Cost of Earthwork in India (2025-26 Rates)
Earthwork rates vary dramatically based on soil type, depth, and city. Here are typical rates per cubic metre:
| Type of Earthwork | Rate per m³ (₹) | Measurement Ref |
|---|---|---|
| Ordinary soil excavation (0-1.5m depth) | ₹150-250 | IS 1200 Part 1 |
| Ordinary soil (1.5-3.0m depth) | ₹200-350 | IS 1200 Part 1 |
| Hard soil / murrum excavation | ₹300-500 | IS 1200 Part 1 |
| Soft rock (weathered) | ₹600-1,000 | Separate item |
| Hard rock blasting | ₹1,200-2,500 | Separate item |
| Filling with excavated earth (within 50m lead) | ₹100-180 | IS 1200 Part 1 |
| Filling with borrowed earth (including transport) | ₹250-500 | Lead charges extra |
| Sand filling (in foundation/plinth) | ₹1,800-3,500 | Based on sand rate |
| De-watering (per hour) | ₹300-600 | Pump + operator |
Worked Example: Foundation Excavation Cost
For a residential building, 10m × 10m plan, strip foundation 1.2m deep × 0.9m wide:
- Perimeter trench: (10+10+10+10) × 1.2 × 0.9 = 43.2 m³ of ordinary soil excavation
- At ₹200/m³: Excavation cost = ₹8,640
- Refilling: ~60% of excavated soil used for backfilling = 25.9 m³ × ₹120/m³ = ₹3,108
- Disposal of surplus: 17.3 m³ × ₹180/m³ (including lead) = ₹3,114
- Total earthwork cost: ~₹14,862
Machine vs Manual Excavation
| Parameter | Manual | JCB/Excavator |
|---|---|---|
| Rate | ₹150-300/m³ | ₹80-150/m³ |
| Speed | 2-3 m³ per worker per day | 80-120 m³ per day |
| Best for | Small trenches, tight spaces | Open foundations, large sites |
| Typical machine hire | — | ₹1,500-2,500/hour (JCB) |
For small residential projects, manual excavation is common. For anything above 50 m³, machine excavation is more economical.
IS Code References for Earthwork
- IS 1200 Part 1:1992 — Method of measurement of building works: Earthwork
- IS 2720 (various parts) — Methods of test for soils (moisture, density, bearing capacity)
- IS 3764:1992 — Excavation work: Code of safety
- IS 6403:1981 — Code of practice for determination of bearing capacity of shallow foundations
Next Steps
- Quantity Takeoff Methods – Long wall, short wall, centre line for building foundations
- Detailed Estimates – Full estimate including earthwork
सामग्री लागत की गणना करें
अपनी परियोजना लागत का अनुमान लगाने के लिए हमारे कैलकुलेटर का उपयोग करें।
कैलकुलेटर खोलेंनिर्माण प्रबंधन विशेषज्ञ
वरिष्ठ निर्माण सलाहकार at Yojo
10+ वर्ष अनुभव
समीक्षा की तारीख 18 मई 2026
Yojo Team के बारे में
10+ वर्षों के अनुभव वाले निर्माण प्रबंधन विशेषज्ञ, भारतीय ठेकेदारों को बेहतर व्यवसाय बनाने में मदद करते हैं। निर्माण साइटों के लिए डिजिटल परिवर्तन में विशेषज्ञ।