Introduction

Quantity takeoff means measuring volumes and areas from drawings to arrive at material quantities. For buildings, earthwork, foundation concrete, brickwork in plinth and superstructure can be worked out by two main methods:

  1. Long wall – short wall method
  2. Centre line method
  3. Partly centre line and partly long wall–short wall

This guide explains each method with a worked example for a single-room load-bearing structure.

Long Wall – Short Wall Method

Definitions

  • Long wall – Wall along the length of the room
  • Short wall – Wall perpendicular to the long wall

How to Get Lengths

  1. Find centre line lengths of each wall.
  2. Long wall (out to out) = Centre line length + (½ × breadth) at each end
  3. Short wall (in to in) = Centre line length − (½ × breadth) at each end

As you move from earthwork → foundation → footings → basement → superstructure:

  • Long wall length decreases (breadth reduces)
  • Short wall length increases

Quantity = Length × Breadth × Height (or depth).

Example: Single Room 5.3 m × 4.3 m (internal)

Assume:

  • Foundation width: 0.9 m, depth: 1.4 m (0.3 + 0.5 + 0.6)
  • CC bed: 0.9 m × 0.3 m
  • RR masonry footings: 0.6 m × 0.5 m
  • RR masonry basement: 0.45 m × 0.6 m
  • Brickwork superstructure: 0.30 m × 3.0 m

Centre line length = 2 × (5.3 + 4.3) = 19.2 m

Earthwork excavation:

  • Long wall L = 5.3 + 0.45 + 0.45 = 6.2 m
  • Short wall L = 4.3 − 0.45 − 0.45 = 3.4 m
  • Q = 2 × 6.2 × 0.9 × 1.4 + 2 × 3.4 × 0.9 × 1.4 = 24.192 cum

CC (1:4:8) bed:

  • Q = 2 × 6.2 × 0.9 × 0.3 + 2 × 3.4 × 0.9 × 0.3 = 5.184 cum

RR masonry footings:

  • Long wall L = 5.3 + 0.3 + 0.3 = 5.9 m
  • Short wall L = 4.3 − 0.3 − 0.3 = 3.7 m
  • Q = 2 × 5.9 × 0.6 × 0.5 + 2 × 3.7 × 0.6 × 0.5 = 5.76 cum

RR masonry basement:

  • Long wall L = 5.3 + 0.225 + 0.225 = 5.75 m
  • Short wall L = 4.3 − 0.225 − 0.225 = 3.85 m
  • Q = 2 × 5.75 × 0.45 × 0.6 + 2 × 3.85 × 0.45 × 0.6 = 5.184 cum

Brickwork superstructure:

  • Long wall L = 5.3 + 0.15 + 0.15 = 5.6 m
  • Short wall L = 4.3 − 0.15 − 0.15 = 4.0 m
  • Q = 2 × 5.6 × 0.30 × 3.0 + 2 × 4.0 × 0.30 × 3.0 = 17.28 cum (before door/window deductions)

Centre Line Method

When to Use

Suitable when walls have similar cross-section. Total centre line length × breadth × depth gives quantity in one step.

Junction Adjustment

Where cross walls or partitions join the main wall, reduce centre line by half the breadth for each junction.

Total centre line = sum of all walls − (½ × breadth) × number of junctions

Same Example by Centre Line

Centre line length = 2(5.3 + 4.3) = 19.2 m (no internal walls)

Earthwork excavation:

  • Q = 19.2 × 0.9 × 1.4 = 24.192 cum

CC bed:

  • Q = 19.2 × 0.9 × 0.3 = 5.184 cum

RR masonry footings:

  • Q = 19.2 × 0.6 × 0.5 = 5.76 cum

RR masonry basement:

  • Q = 19.2 × 0.45 × 0.6 = 5.184 cum

Brickwork superstructure:

  • Q = 19.2 × 0.30 × 3.0 = 17.28 cum

Same answers as long wall–short wall, with less calculation.

Partly Centre Line and Partly Long Wall–Short Wall

Use when:

  • External walls – Same thickness all around → centre line method
  • Internal walls – Different thickness or levels → long wall–short wall method

This is common in practice for buildings with different foundation levels or wall thicknesses.

Choosing a Method

SituationPreferred method
Simple rectangular room, same sectionCentre line
Multiple rooms, different wall thicknessesLong wall–short wall or partly centre line
Symmetrical layoutCentre line
External + internal with different sectionsPartly centre line

Deductions for Openings

For brickwork in superstructure, deduct door and window openings:

Deduction = Opening length × Wall thickness × Opening height

Deduct lintel volume separately if required. Net brickwork = Gross − Deductions.

Next Steps

सामग्री लागत की गणना करें

अपनी परियोजना लागत का अनुमान लगाने के लिए हमारे कैलकुलेटर का उपयोग करें।

कैलकुलेटर खोलें
इस लेख को साझा करें:
समीक्षा की गई

निर्माण प्रबंधन विशेषज्ञ

वरिष्ठ निर्माण सलाहकार at Yojo

10+ वर्षों का अनुभवप्रमाणित निर्माण प्रबंधक

10+ वर्ष अनुभव

समीक्षा की तारीख 10 मार्च 2026

Y

Yojo Team के बारे में

10+ वर्षों के अनुभव वाले निर्माण प्रबंधन विशेषज्ञ, भारतीय ठेकेदारों को बेहतर व्यवसाय बनाने में मदद करते हैं। निर्माण साइटों के लिए डिजिटल परिवर्तन में विशेषज्ञ।

निर्माण प्रबंधन विशेषज्ञ10+ वर्षों का अनुभव
विशेषज्ञता:
निर्माण प्रबंधनश्रम प्रबंधनसाइट संचालन

अक्सर पूछे जाने वाले प्रश्न

Yojo ऐप डाउनलोड करें

WhatsApp पर Play Store लिंक पाएं।

मुफ्त डाउनलोड

आप भी पसंद कर सकते हैं

Detailed Estimate of Buildings: Step-by-Step Guide (Free Format Inside)
Cost & Estimation

Detailed Estimate of Buildings: Step-by-Step Guide (Free Format Inside)

Prepare detailed building estimates in 7 steps — measurement forms, abstract of cost, item-wise rates. Single-room + two-room examples with free format inside.

और पढ़ें
Units of Measurement in Construction (IS 1200)
Cost & Estimation

Units of Measurement in Construction (IS 1200)

Learn how construction work is measured in India—numbers, running metres, sq m, cum. IS 1200 units for earthwork, concrete, brick, steel, plastering, and more.

और पढ़ें
10×10 कमरा: कितनी ईंट, सीमेंट, रेत चाहिए? | मुफ्त कैलकुलेटर
Cost & Estimation

10×10 कमरा: कितनी ईंट, सीमेंट, रेत चाहिए? | मुफ्त कैलकुलेटर

10×10 फुट कमरे में ~1,450 ईंटें (₹7,250), 35 सीमेंट बैग (₹12,250), 2.5 m³ रेत। अपने कमरे का साइज़ डालें, तुरंत अनुमान पाएं।

और पढ़ें
Earthwork Calculation: Excavation & Filling Volume (Trapezoidal Formula)
Cost & Estimation

Earthwork Calculation: Excavation & Filling Volume (Trapezoidal Formula)

Calculate earthwork excavation and filling quantities step-by-step. Trapezoidal & prismoidal volume formulas with worked examples for roads, foundations, trenches.

और पढ़ें
1000 Sq Ft Ghar Banana Ka Kharcha 2026 — Pura Hisab
Cost & Estimation

1000 Sq Ft Ghar Banana Ka Kharcha 2026 — Pura Hisab

2026 mein 1000 sq ft ghar banana ka kharcha ₹12–₹22 lakh aata hai. Material, labour, foundation se finishing tak — pura cost breakdown yahan dekhein।

और पढ़ें
Cement Kitna Lagega? — Free Calculation Guide
Cost & Estimation

Cement Kitna Lagega? — Free Calculation Guide

Cement kitna lagega — har kaam ke liye cement calculate karna seekhein. Brickwork, plastering, RCC slab, flooring ka complete formula aur table।

और पढ़ें

साइट से सैलरी तक, सब ट्रैक करें

Yojo डाउनलोड करें

एंड्रॉइड पर मुफ्त

Get it on Google Play
Yojo app language selection — Hindi, Marathi, Tamil and more
Yojo construction app dashboard